509-838-8000

Projects

Armature Repair

Oregon Steel

Rewinding of a Double Armature on a common shaft with a rating of 1750 HP per armature, totaling 3500 HP. This unit originally was used on a US Navy Submarine for their propulsion system.

3500 HP Equipment Rating
$329,464 Contract Value
April 2009 Completion Date

Bolivar Gold Mill Expansion

Bolivar Gold

Reconditioned two Ball Mill Motors. Supplied new brushes and brush holders, and crated for shipment to job site. Rebabbitted both sleeve bearings for both motors. Rewound 1 each stator, turned rings on both. Performed final test run prior to crating and shipping.

Two 2750HP sync GE Equipment Rating
$170,000 Contract Value
March 2004 Completion Date

Stator rewind

Smurfit

Cleaned, tested, treated, and balanced rotor in shop. Onsite, strip, and clean stator. Cut and install slot insulation. Insert coils, block and tie end turns, connect coils, test, treat, and bake. Retest, re-assemble unit, and align. Test run. Completed commissioning by vibration analysis and bearing. Temperature monitoring over 24-hrs.

7500KVA, 3800RPM, Steam Turbine Generator Equipment Rating
$438,000 Contract Value
March 2009 Completion Date

Box Canyon Power House Crane

Pend O'rielle County PUD

Redesigned from single cab to a dual cab and electrical equipment room. Fabricated both operator's cab and electrical equipment room.

100 Ton Equipment Rating
$142,600 Contract Value
March 2008 Completion Date

Round Butte Dam Hydro Project Selective Water Withdrawal Structure

Portland General Electric

In 2007, Portland General Electric (PGE) and the Warm Springs Tribe of Indians began work on the latest improvements to the 40 year old Pelton Round Butte Dam Hydroelectric project. The objective was to construct a $130M facility that would meet the tightening regulatory requirements under their federal operating license. This one-of-a-kind project is known as the Selective Water Withdrawal (SWW) facility, and was completed in Spring 2009.

The SWW is a 260 foot tall, 6.5M lb structure, built of steel and concrete in four major components: the selective water bottom (SWB), the vertical flow conduit (VFC), the selective water top (SWT), and the fish transfer facility (FTF). Due to the size and nature of the project, the components were built independently in the water. The SWT and FTF are floating structures.

The different types of equipment that K&N provided on this project are as unique as the project itself. Cranes, compressed air systems, process control systems, and hydraulic gates located 250 feet below the lake surface are just a few of the distinctive features that K&N was responsible for.

The SWW will modify the surface currents in Lake Billy Chinook to mimic the downstream flow of the three contributing rivers in order to aid fish migration. The SWW is designed to pass the entire flow of the Deschutes and Metolius Rivers through the top (SWT) structure. The major objectives of this project are to reorient the surface currents toward the dam, safely capture migrating salmonids, and manage downstream water quality during seasonal discharge events. This will all be accomplished while meeting discharge permit regulations and maintaining hydroelectric generation capacity. This project stands as the largest hydro project contained entirely within the state of Oregon.

Submerged (-250 ft) Equipment Rating
$10,000,000 Contract Value
April 2009 Completion Date

Post Street Substation Install Reactor and Switchgear Floor

Avista Corp.

This project had many challenges: it was a fast track project, performed in a dangerous electrical environment, requiring the incorporation of new structural components into a historical building and all this without interrupting the electrical power supply to the Downtown Spokane area. We were contracted to fabricate and install a new flooring system incorporating structural fiberglass and steel components. All work, including change orders, was completed within the schedule. Changes were minor and resulted from differing site conditions. A universal 3-dimensional drafting program was utilized by the design department to compile the details of materials provided from all the various suppliers. This assured a quality of detail that was outstanding and very necessary to the quick start-up and completion of the project. A sample detail is shown.

Deck Load Rating:

  • 75 psf live load with 1/8" maximum deflection
  • 150 psf live load, no deflection limitation
  • 300 lb. point load on 2" x 2" square

$180,000.00 Contract Value
2/13/04 Completion date

Cougar Dam Bridge Crane Rerate

U.S.A.C.E. Portland District

This project required the retrofit of controls and equipment for rerating the bridge crane from 60T capacity to 62.5T capacity. Provided mechanical, structural and electrical modifications as follows: perform pre-rehabilitation inspection and report, remove all power and control systems including motors, drive systems, conduit, and wiring, and remove the back panels in existing control cabinets leaving the cabinets to be re-used. Design, fabricate and install new master switch console. Design, furnish, and install AC variable frequency vector drives, install dynamic braking resistors and isolation transformers, install replacement AC induction hoist motors, bridge and trolley brake motors (25HP, 10HP and .75 HP), main line contactor, main circuit breaker, cable track system, control relays, speed encoders, brake rectifiers. Included in the modernization were couplings, alignment, electrical buss guard and hook safety latches. Performed structural analysis to verify adequacy of walkway to support additional loading, and to determine method of spreading test loads on erection bay floor. Final acceptance tests, including load test, and operation and maintenance training were provided. Final submittals included as-built drawings and operation and maintenance manuals.

65 Ton Equipment Rating
$351,893.00 Contract Value
8/1/2003 Completion

We provided all project management functions including: Design, management, procurement, manufacturing management, subcontract administration, quality control, submittals, schedules, as well as contractual matters with the owner.

We provided manufacturing, field mechanical and structural work, and field electrical.

Specific equipment to be supplied, manufactured and installed includes: new hoist motors, brake motors, AC Flux Vector Drives, transformers, resistors, couplings, cable track system, hook safety latches, electrical buss guard, and operators control console. Items installed and connected by our field electrical wiremen are:

Power, hoist and drive cabinets and system components.

Brake controllers, resistor cabinets, motors and control/limit switch devices.

Raceways and conduit systems, encoders, cable track system and supports.

Bridge Cranes Rehabilitation, Lookout Point and Dexter Dams, Lowell, Oregon

U.S. Army Corps of Engineers, Portland District

Lookout Point: Rehabilitation of 200T Bridge Crane. The entire crane was inspected and recommendations made to the customer. Main Hoists, Aux. Hoists, Cantilever Hoist, trolley drives, and bridge drives were rehabilitated. Engineering lift plans were developed for replacement of large components. Safe access was provided throughout the crane per OSHA & EM-385. New operators cab, hoist drums & gears were provided.

Dexter: Rehabilitation of 100T Bridge Crane. The entire crane was inspected and recommendations made to the customer. Main Hoists, Aux. Hoists, trolley drives, and bridge drives were rehabilitated. Engineering lift plans were developed for replacement of large components. New operators cab, hoist drums & gears were provided.

Statistical / Equipment Rating

Hoisting Capacity

  • Lookout Point
    • Main hoist, 2 each 100 Tons, total capacity 200Tons
    • Aux hoists, 2 each at 15 tons
    • Cantilever Hoist 7.5 Tons
    • Bridge Span 60 feet
  • Dexter
    • Main Hoist, 2 each at 50 Tons; total capacity 100 Tons
    • Aux Hoists, 2 each at 15 tons
    • Bridge Span 52 feet

Hoist Travel Speeds

  • Lookout Point
    • Main Hoist, 5 feet per minute, travel range 61 vertical feet
    • Aux Hoists, 20 feet per minute, travel range 73.5 vertical feet
    • Cantilever Hoist, 20 feet per minute, travel range 60 vertical feet
  • Dexter
    • Main Hoist, 5 feet per minute, travel range 60 vertical feet
    • Aux Hoists, 25 feet per minute, travel range 75 vertical feet
  • $5,335,000 Contract Value
    12/29/08 Completion date

Other Projects

General Dynamics, Inflation Systems—Develop and automate charge system process control to PLC based system and integrate into existing plant protocol

Lower Granite Turbine Runner Rebuild—Manufacture, Machine and supply all replaced components for turbine runner including large bore, 46" bushings, linkages and OEM replacement parts

Rock Island Dam Tailrace Unit Dewatering Pumps and Control—Manufacture, Install and commission critical redundant PLC control, interfaced with plant operating and monitoring systems

Ice Harbor Dam Switchgear relay replacement and retrofit—Replacement of outdated protective relays and controls to SEL systems

Dalles 100 Ton Intake Gantry Crane Modernization—Complete mechanical and electrical modernization of Hydro plant gantry crane

Rocky Reach 01-50 Juvenile Fish Bypass Project—Design, Manufacturing, Installation and Testing of equipment for final developed bypass system. Radial gates and control, hydraulic systems, PLC control System and Main power Systems.

McNary Dam Cranes Rehabilitation—Complete mechanical and electrical rehabilitation and upgrade for 2 powerhouse bridge cranes 350Ton, 1 draft tube Gantry, 20Ton and 1 Intake Gantry Crane,140 Ton

Cougar Dam Crane Uprate—Rehabilitation and control upgrades for re-rate from 60 to 62.5 Ton Capacity, utilizing flux vector VFD system.

Little Goose Dam, Intake Gantry Modernization—Complete design and electro - mechanical crane upgrade of 100 Ton gantry crane.

Chief Joseph Dam, Bridgeport, WA: Crane Modernization—Intake Gantry with main, aux and hammerhead hoists, two 165T Powerhouse Bridge, and Tailrace Gantry Cranes: Design through certification

Equilon Refinery, Anacortes, WA: Crane Modernization—17T Coke Pit Semi Gantry Crane.

Idaho Forest Industries, Coere d'Alene, ID—Headrig Carriage Modernization Motor, reducer, wire rope drum, encoders, shafts, bearings, couplings, hydraulic take-up unit, wire rope sheaves.

Deer Island Treatment Plant, Boston, MA—Hummer Engine and Outboard Motor Engine Intake Oxygen Control System To permit diesel operation in oxygendepleted tunnel environment, a PLC-controlled valve metered O2 to the engines' inlets via feedback from an O2 sensor on the mix side. Complied with requirement that rented vehicles shall not be modified for the system installations.

Ship Model Engineering and Support Facility, Bayview, ID—Hatch winches

Bonneville Lock and Dam, Portland, OR: Crane Modernization—350T Spillway Gantry Crane.

Glenn-Calusa Irrigation District, Hamilton, CA—Fish Screen Cleaning System Largest known screen cleaner system to date

Bonneville Lock and Dam—Manufacture 4 Automated Spillway Gate Hoists 390 Ton

Rocky Reach Dam Fish Operations 2000, Wenatchee, WA—Vertical brush screen sweep (hoist) modifications: shafting, load cell modifications, guide wheels

Folsom Dam, Folsom, CA—Water Supply Intake Temperature Control Device Water quality analyzer.

Kaiser Aluminum, Spokane, WA: Crane Modernization—15T Sonic Inspection Bay Crane. Developed and installed redesign and Wrote/conducted separate certification tests.